Responding to a Standard and/or Change End Date Modification

Once the CO initiates the modification, you will get an e-mail message and an alert message on the main Home page informing you that the agreement you have has a modification.

Alert message about a modified agreement.

Business Rules for Standard and/or Change End Date Modification

When responding to a standard and/or change end date modification, you should be aware of the business rules that will be applied.

To respond to a standard and/or change end date modification:

  1. From the Alert message, click on the Review Changes link OR from the Home page, click on the My Agreements tab to find the modification in progress. 
  2. In the Agreement table, notice the indented row under the agreement, which indicates there is a modification to the agreement and displays the following information about the modification:

Notice in the Response Status column the status is "Awaiting Vendor Signature."

  1. In the table, in the Action column, click on the Submit a response to this modification icon (Start a modification response.) to open the Agreement Modification Response wizard.
  2. In the Review Modification step, view the Modification Summary, which includes a description of the modification. For more details, click on the View Mod PDF button (View the solicitation PDF).
  3. Click the Continue button to proceed to the next step.
  1. In the Apply Resource Changes step, in the Action column, from the drop-down list, select the appropriate action you wish to make with the standard and/or change end date modification. Your choices are No Changes to Resource, Updates to Resource, Replace Resource, and Withdraw Resource.

NOTES:
- To understand the Action options, click on the Definitions of the Action options link above the table.
- If you have changed a resource so that it no longer qualifies on the agreement, and you respond to a modification without re-qualifying your resource, then you will only see Replace Resource and Withdraw Resource as Action options to select. Contact your Contracting Officer to discuss the disqualification.

  1. In the Resource Comparison table, view the changes from your original resource to your current resource, and then click the OK button. (To view the Resource Comparison table, click on the magnifying glass icon [View the Resource Comparison dialog box.].)

NOTE: Changes to your resource are highlighted in bold, red text in the right column of the Resource Comparison dialog box.

  1. Click the Continue button to proceed to the next step.
  1. In the Resource Comparison table, view the changes from your original resource to your current resource, and then click the OK button. (To view the Resource Comparison table, click on the magnifying glass icon (View the Resource Comparison dialog box.).)
  2. Click the Continue button to proceed to the next step.
  1. In the Sign Modified Agreement step, click the Preview Modification Response button to view modification response package which lists your resources and their attributes and highlights any attribute changes that you wish to make through the modification.
  2. Read the modification signature statement and if you agree to the statement, select the 'I Agree' check box.
  1. Click the Submit button to submit your signed agreement modification submission.
IMPORTANT
If you have an expired SAM record or your company name, DBA, company address, or mailing address in VIPR is different than what is in your SAM record, then you will be unable to submit your response to the modification. Depending on the issue, you must go through SAM to activate your SAM record OR use the "View/Import from SAM" button in the vendor application to get your VIPR company information in sync with SAM. Once the SAM issue is resolved, you can submit the modification response. For more information, see "The VIPR/SAM Interconnection".
  1. Once you receive confirmation that your response was successfully submitted, click the Exit button to exit the wizard.
  2. In the My Agreements table, notice the Status column has a status of "Awaiting Contracting Officer Signature."

Once the CO signs the modification, the following occurs:

If you have any questions or concerns regarding the modification, contact the CO. Also, you should print the agreement for your records (see "Printing an Agreement").

Related Topics Link IconRelated Topics